What we do
Select a service to view deep technical scope, tools/instruments, methodology, standards & deliverables.
Energy Audit Consulting
Electrical EPC Project Consulting

Energy Audit & Optimization
We execute comprehensive energy studies as per BEE guidelines and ISO 50001—covering electrical, thermal, HVAC, utility, and process loads with measurement-driven diagnostics and ROI-linked recommendations.
BEE aligned ISO 50001 Tariff & Demand ReliabilityScope
- Electrical: transformer loading/losses, PF correction (fixed vs APFC/hybrid), harmonics (THD), demand & TOD tariff optimization.
- Drives & Rotating: motors/pumps/compressors/blowers—duty cycles, IE2/IE3/IE4 benchmarking, VFD retrofits, shaft power estimates.
- HVAC/Utilities: chiller COP, condenser/evaporator approach, CT performance, AHU balancing, compressed air leak mapping.
- Lighting: LUX mapping vs IS recommendations, fixture efficacy, daylight/occupancy automation & controls.
- Process/Thermal (where applicable): heat balance, waste heat recovery, insulation audits, combustion tuning.
Tools & Instruments We Use
- 3-Phase Power Quality Analyzer: V/I, kW/kWh, PF, THD, harmonic spectrum, demand profile (7–14 day logging).
- Clamp Meters/Data Loggers: current/voltage/temp/RH/dP; correlation with production & weather.
- Thermal Imaging: hotspots on panels/busbars/bearings/cables; insulation integrity & temperature rise checks.
- Ultrasonic Leak Detector: compressed air/vacuum leaks, leak tagging & quantified savings.
- Lux Meter, Anemometer/Manometer: lighting level & airflow diagnostics, duct static pressure.
- Vibration Monitoring: bearings/misalignment; conditional maintenance inputs.
- DLRO (as required), IR/PI (Megger), and for thermal plants Flue Gas Analyzer.
Indicative brands: Fluke / HT Italia / Testo or equivalents. Selection depends on rating & HIRA.
Methodology & Approach
- Baseline: SLD review, load tree, 12-month bills, interval data, production correlation & seasonality adjustments.
- Measurement plan: CT/PT ratio verification, logging strategy, safety permits & LOTO compliance.
- Diagnostics: PQ & harmonics source tracing, transformer %loading, cable temp rise, motor slip/efficiency checks.
- HVAC/Utility deep-dive: COP/delta-T, pump curves vs duty point, VFD logic, AHU optimization, leak quantification.
- Opportunity register: no/low/capex ECMs with kWh/kVAh/thermal savings & reliability impact quantified.
- Financials: payback/IRR/NPV, M&V plan (IPMVP-style), and phased implementation roadmap.
Deliverables
- Audit Report: instrument traces, heat maps, LUX charts, PQ trend plots, and root-cause analysis.
- Opportunities Matrix: savings, cost, payback, dependencies; retrofit BOM/specs.
- Implementation plan: sequencing, shutdown windows, contractor scope, risk controls & QA checks.
- M&V protocol and KPI dashboard (monthly scorecard for management review).
Standards & Codes (Indicative)
- BEE Energy Audit Guidelines; ISO 50001 EnMS framework.
- IS 3043 (Earthing), IS 732 (Electrical Installations), cable/XLPE per IS/IEC.
- IEEE 519 (Harmonics), IEC 60034 (Rotating Machines) for motor efficiency classes.
- Safety audit alignment to IS 14489; permit-to-work & LOTO procedures.